ERP implementation steps from discovery to handover

The new ERP must become a part of everyday life while the company's work continues. Implementation is more successful when responsibilities, data transfer, testing and user orientation are planned in time. This guide shows what is done at different stages of the project and what is needed from the customer.

We describe the work phases of Datastorm turnkey delivery from survey to commissioning day. The customer gets the agreed entity ready for use. During implementation, the system is collectively reviewed and tested with real workflows; maintenance and support are agreed upon separately.

What are the stages of the ERP project?

ERP delivery includes mapping needs, defining the entire delivery, implementation, testing, commissioning, and agreeing on maintenance. These are the work stages of a single turnkey delivery. The content, cost estimate, schedule and acceptance criteria are agreed upon in writing before implementation.

Phase Indicative duration What is born What is needed from the customer
1. Mapping About a week Process description, objectives, rough hourly estimate and offer Decision maker and process owners, 2-4 hours of shared time
2. Light definition 1-2 weeks View Drafts, Data Model, Integration List, Detailed Review Comments on drafts, approval of the full project scope
3. Implementation of the agreed entity According to agreed delivery content Agreed workflows, views, reports and integrations Test data, logins to interfaces, weekly 30 min review
4. Testing and piloting 2-4 weeks Corrected version, user manual and training material Pilot team and 5-10 hours of testing time per person
5. Entire company deployment 1-2 weeks All users in the system, data transferred, old way out Training time, cleaned old data, decision on transition date
6. Further development Ongoing agreement New features, integrations, maintenance and support Contact person and monthly prioritization

Step 1: What is done in the survey?

A survey is a 10- to 20-hour job of reviewing the company's current processes step by step and recording where information is rewritten, where it is necessary to ask a colleague, and where mistakes are made. The end result is a process description, a list of objectives in order of priority and an offer showing the number of hours and the amount of euros. The price is 700-1400 € + VAT.

It is advisable to order a survey even when no purchase decision has been made. Even from the offer you can see what the price would be for having your own system, and that is the information without which it is difficult to make the whole comparison. A bid may also be requested when a decision has not yet been made on the project.

Step 2: Why is the definition kept light?

Light definition means that the data model, view sketches and integration demarcations are recorded – But not a hundred-page document that no one reads. Heavy definition locks decisions at the moment when they are least known, and each subsequent change appears to be a deviation from the plan.

In practice, a good definition can fit in a few pages and a few sketches. Its job is to make sure that we are talking about the same thing and that the hourly estimate is realistic. The rest of the clarifications are made when the view is already on the screen and you can say an opinion about it.

Step 3: What is included in the finished ERP delivery?

The completed ERP includes agreed workflows, user roles, views, reports, and integrations. In addition, the implementation includes agreed data transfers, testing, induction and documentation. Functions and acceptance criteria are recorded before construction. See ERP system price and schedule.

The content of the delivery is determined by your company's operations. Orders, inventory, work management and billing must form an agreed-upon functional entity. The implementation of an individual workflow is illustrated by a guide Product Life Cycle in ERP.

Step 4: How will the testing and pilot be carried out?

A pilot with one team reveals the problems that no one can come up with in the meeting room and does it when fixing is still cheap. The pilot team uses the system for real work for two to four weeks in parallel with the old way, so that errors do not bring down the entire company. The pilot also creates the first internal experts who teach others how to use them better than an external trainer could ever do.

As a pilot team, you should choose the group that makes the process the most – Not the one who is most positive about change. A critical user finds problems faster, and once convinced, it is easy to convince the rest of the organization.

Step 5: How is the introduction of the whole company done?

Enabling the whole company is a short step if the previous ones are done properly. In practice, a transition date is chosen, the final data transfer is run the night before, short trainings are held by user group and we are able to reach the first days more closely than usual. The old habit is closed at the same time, because parallel use for longer than a few weeks always leads to some remaining in the old one.

Step 6: What happens after deployment?

In connection with the Datastorm ERP system to be delivered to production, continuous maintenance and technical partnership will be agreed. The purpose of the continuous service is to ensure that the system has a designated technical partner who is responsible for maintenance, support and further development in accordance with the agreed service level. The first few months often go to minor repairs and usability refinements, because proper use always reveals things that testing did not reveal. The work then turns to new features and integrations, and the system evolves at the same pace as the business.

What is required of the client in an ERP project?

Four things are needed from the customer: one decision maker with the authority to decide, process owners who know how the work is actually done, test data, i.e. real orders and products and not invented examples, and time for testing. It typically takes 2-4 hours for the survey to be completed, a few hours for the specification to be commented on, and 5-10 hours per person in the pilot phase. This is the most important resource of the project, and lack of it is the most common reason for the schedule to be stretched.

The role of the decision-maker deserves its own attention. Development always stops if a simple question is not answered within a week. In practice, the most effective arrangement is one named person who can decide for themselves and is reachable within a week. The committee is not suited to this role.

Process owners are the people who do the work every day. Their knowledge is invaluable because the recorded process and the actual process are almost always different from each other – and the system must be built according to the real. One hour with a warehouse worker between the shelves is worth more than three hours in a conference room.

How to transfer old data from Excel and old systems?

The data is transferred in three batches: first the basic data such as products, customers and suppliers, then the open transactions such as unfinished orders and stock balances, and finally the history to the extent that it is actually needed. It is a good idea to run the transfer as an exercise at least twice before the actual commissioning, so that incorrect lines can be repaired in peace. The biggest job is not the move, but the cleanup, because old Excel files almost always have duplicates, missing fields, and names written in different ways.

In terms of history, it pays to be ruthless. Moving a ten-year order history to a new system costs a lot and rarely yields a similar benefit. In most cases, it is enough to keep the old system or Excel archive in read mode and move open events to the new one, as well as one or two years of history. Data transfer is typically 15-40 hours of work, or 1,500-4,000 € + VAT, depending on the number of sources and how cool the data is.

How is training and documentation handled?

In a customized system, the training need is small, because the views are made for the exact work steps that the user does, and there are no fields on the screen that are not used in the company. In practice, it is enough to go through one hour per user group, as well as a short written instruction and a few screenshots of the most common workflows. However, the best training is the pilot phase, where a few employees learn the system in the right job and then guide their colleagues.

It is best to keep the documentation light but on two levels. For users, a brief instruction per workflow is sufficient. The company itself also needs a technical description of where the system is installed, what integrations are in place, where the backups are and by whose credentials what can be achieved. This second level is the one that is forgotten and missed when there is none.

Why do ERP projects fail?

The risks of an ERP project include changing delivery content, delayed decisions, inadequate source data and insufficient testing. We manage them through written delivery content, joint revisions, data transfer training times, and user acceptance testing. The commissioning is planned according to the company's everyday life, and the maintenance responsibility is agreed in advance.

Reason for failure How to manage risk
The definition swells and the project does not start The specification is light and lasts 1-2 weeks, the rest will be specified along the way
No decisions are made, the schedule is stretched One named decision maker is already agreed upon in the survey
Everything is enabled at once and nothing works The agreed entity is tested, users are familiarized and a plan is made for the transition
Old data only proves messy at the end Data transfer is practiced at least twice before commissioning
Users do not want to use the system Views are planned with the process owners and the pilot lets influence
The system lags behind the business Further development and maintenance will be agreed before commissioning.
Supplier disappears after deployment Code and environments are customer's own and documented, follow-up will be agreed in advance

How long does it take to deploy an ERP system?

The delivery time is determined by the agreed entity, integrations and data to be transferred. In one of the projects we carried out, the call for tenders came in mid-March, the purchase decision in early April and the system was available to the entire company on May 25. It took about ten weeks from the call for tender to commissioning. The schedule for your project will be agreed upon in the offer.

AI-assisted development has shortened the implementation work of Datastorm. It does not eliminate the need for design, testing or orientation. We agree on a schedule for the entire ready-to-use delivery and also reserve time to review and deploy the data.

The delivery schedule is also affected by the identifiers of external services, the quality of the data to be transferred and the testing of users. We agree on these responsibilities and schedules in advance. Datastorm is responsible for technical work; your company's contact person will confirm the policies and necessary decisions.

Frequently Asked Questions About ERP Deployment

What are the stages of the ERP project?

ERP delivery includes mapping needs, defining the entire delivery, implementation, testing, commissioning, and agreeing on maintenance. These are the work stages of a single turnkey delivery. The content, cost estimate, schedule and acceptance criteria are agreed upon in writing before implementation.

How long does it take to deploy an ERP system?

The delivery time is determined by the agreed entity, integrations and data to be transferred. In one of the projects we carried out, the call for tenders came in mid-March, the purchase decision in early April and the system was available to the entire company on May 25. It took about ten weeks from the call for tender to commissioning. The schedule for your project will be agreed upon in the offer.

What is required of the client in an ERP project?

Four things are needed from the customer: one decision maker with the authority to decide, process owners who know how the work is actually done, test data, i.e. real orders and products and not invented examples, and time for testing. It typically takes 2-4 hours for the survey to be completed, a few hours for the specification to be commented on, and 5-10 hours per person in the pilot phase. This is the most important resource of the project, and lack of it is the most common reason for the schedule to be stretched.

How to transfer old data from Excel and old systems?

The data is transferred in three batches: first the basic data such as products, customers and suppliers, then the open transactions such as unfinished orders and stock balances, and finally the history to the extent that it is actually needed. It is a good idea to run the transfer as an exercise at least twice before the actual commissioning, so that incorrect lines can be repaired in peace. The biggest job is not the move, but the cleanup, because old Excel files almost always have duplicates, missing fields, and names written in different ways.

Why is piloting with one team worthwhile?

A pilot with one team reveals the problems that no one can come up with in the meeting room and does it when fixing is still cheap. The pilot team uses the system for real work for two to four weeks in parallel with the old way, so that errors do not bring down the entire company. The pilot also creates the first internal experts who teach others how to use them better than an external trainer could ever do.

Why do ERP projects fail?

The risks of an ERP project include changing delivery content, delayed decisions, inadequate source data and insufficient testing. We manage them through written delivery content, joint revisions, data transfer training times, and user acceptance testing. The commissioning is planned according to the company's everyday life, and the maintenance responsibility is agreed in advance.

What happens after the introduction?

In connection with the Datastorm ERP system to be delivered to production, continuous maintenance and technical partnership will be agreed. The purpose of the continuous service is to ensure that the system has a designated technical partner who is responsible for maintenance, support and further development in accordance with the agreed service level. The first few months often go to minor repairs and usability refinements, because proper use always reveals things that testing did not reveal. The work then turns to new features and integrations, and the system evolves at the same pace as the business.

Do you need separate training for ERP deployment?

In a customized system, the training need is small, because the views are made for the exact work steps that the user does, and there are no fields on the screen that are not used in the company. In practice, it is enough to go through one hour per user group, as well as a short written instruction and a few screenshots of the most common workflows. However, the best training is the pilot phase, where a few employees learn the system in the right job and then guide their colleagues.

Summary

Datastorm is responsible for delivering a customized ERP from design to deployment. You will get the agreed entity ready to use, as well as access to source code, your own data, backups and documentation. The price and delivery time are estimated based on your company's needs. See ERP system price and schedule or calculate an indicative estimate.

The single most important factor of success is not technical. It is that there is one person in the company who can decide, and a few people who have time to test. There are better conditions for keeping to the timetable thus agreed. Datastorm Oy and Miko Axel Kallio are building tailored ERP systems for SMEs with this model.

Read also

Author

Miko Axel Kallio

Software developer and founder of Datastorm Oy. Takes customized ERP systems to production in SMEs from mapping to further development.

LinkedIn · Previous content update: 21.10.2026

Shall we begin with the survey?

The mapping is 10-20 hours, and after that you will know in hours and euros what your system would cost and in what time it would be completed. A bid may also be requested when a decision has not yet been made on the project. Read more about how we build Customized ERP system.

Get in touch Arrange a call

What would you like to improve in your business?

Datastorm Oy's ERP delivery is a written agreement, ready-to-use system from design to commissioning. The initial discussion and the offer are free of charge; any separate specification work will be agreed in advance. Maintenance and subsequent further development will be agreed separately. Explore our ERP service.